- General Support
- Oneline & User Interface
- License Key Issues
- Downloading/Installing Software
- Printing
- Reports
- Equipment Modeling
- DAPPER (Demand Load)
- DAPPER (Load Flow)
- DAPPER (Short Circuit)
- CAPTOR (TCC)
- Arc Flash Evaluation
- Equipment Evaluation
- Cable Ampacity
- A_Fault (ANSI)
- IEC 60909 Fault
- IEC 61363 Fault
- TMS (Transient Motor Starting)
- HI_WAVE (Harmonics)
- Unbalanced/Single Phase
- DC Systems Analysis
- GroundMat
- Cable-3D
- Scenario Manager
- Backup & Import/Export
Equipment Evaluation using UBSC results
When evaluating buses using UBSC results, the LVF is still used although it is currently not noted in the software.
The System X/R at the bus is determined by the "ubSC_EquivZ 3P" attribute and used to compare with the Bus X/R. If the System X/R is higher than the test X/R of the bus, then the LVF is calculated using the bus X/R and the system X/R.
The System X/R at the bus is determined by the "ubSC_EquivZ 3P" attribute and used to compare with the Bus X/R. If the System X/R is higher than the test X/R of the bus, then the LVF is calculated using the bus X/R and the system X/R.